Intersection Improvement Projects

The Town of Zebulon is experiencing rapid growth along several major corridors throughout town. As new neighborhoods are built and new residents move into our community, the increased traffic requires changes to our roadways to ease congestion and enable the safe, smooth movement of traffic. The Town is working with the NC Department of Transportation and various engineers, surveyors, contractors, and other firms to design and construct intersection improvements.

One area of rapid growth is near the intersection of Shepard School Road and Old Bunn Road/Proctor Street. A traffic study conducted in January of 2020 indicated that the volume of traffic flowing through the intersection would necessitate a light once the new neighborhoods were fully built. While NCDOT has this project in its long-range plans, the Town of Zebulon is moving forward with funding and constructing the improvements now in recognition of the project's importance to the Zebulon community. Once completed, NCDOT will take over all maintenance and upkeep for the intersection, from the monthly power bills to future infrastructure repairs.

Beginning in November of 2020, the Town is working with consultants, NCDOT, and other state agencies to install turn lanes and traffic signals at this intersection. The final design will improve safety and the flow of traffic. The estimated construction cost is $1.7 million.

Intersecton Plan

 

Project Timeline

PROJECT ACTIVITYSTATUS/ TIMEFRAME
Warrant AnalysisCOMPLETE - Jan 2020
Planning discussions with NCDOTCOMPLETE - Fall 2020
Maintenance Agreement executed with NCDOTCOMPLETE - Jan 2021
Hire engineer for design, environmental permitting, surveying, utility coordination, & erosion controlCOMPLETE - Nov 2020
Survey existing conditions and elevationsCOMPLETE - Mar 2022
30% Construction plans approval from NCDOTCOMPLETE - April 2021
60% Construction plans approval from NCDOTCOMPLETE - Nov 2021
Obtain environmental permitsCOMPLETE - Jan 2022
Secure buffer mitigation creditsCOMPLETE - Jan 2022
Hire right-of-way (ROW) agentCOMPLETE - Mar 2022
Purchase Easements and ROWONGOING
Design water line relocationsCOMPLETE
100% Construction Plans approval by NCDOTCOMPLETE
Complete Bid Documents, Estimates, & SpecsCOMPLETE
Contract for ConstructionSpring 2025
Contract for Construction Administration/CEI ServicesFall 2024
Project ConstructionSpring - Fall 2025
Project CloseoutFall 2025